Every sourcing discussion starts with unit price. Very few start with the calendar, which is strange, because a missed delivery costs far more than a few cents per bottle. In China, packaging capacity is not evenly distributed across the year. There are four windows when it tightens sharply — and all four are predictable years in advance.
This is the big one, and it is larger than the official holiday suggests. The statutory break is around eight days. The actual disruption runs five to six weeks.
| Phase | What happens | Capacity |
|---|---|---|
| 4–6 weeks before | Brands rush to ship before the break. Every plant books out; raw material lead times stretch. | Overbooked — new orders get pushed past the holiday |
| 2 weeks before | Migrant workers begin leaving for home. Lines run short-staffed, then stop. | Falling fast |
| Holiday week | Plant closed. Only security and maintenance on site. | Zero |
| 1–2 weeks after | Workers return gradually. Plants restart with a backlog already queued. | Slow ramp, allocated to oldest orders |
Upcoming dates to work from:
| Year | Chinese New Year | Practical order-by date |
|---|---|---|
| 2027 | 6 February | Early December 2026 |
| 2028 | 26 January | Mid-November 2027 |
Note that 2028 is almost two weeks earlier than 2027. If you plan your year by "last year we ordered in December", the 2028 cycle will catch you out.
Guangdong summers push the grid to its limit, and provincial policy occasionally restricts industrial electricity use. Blow moulding is energy-intensive — extruders and chillers run continuously — so a curb hits our output directly.
In practice this shows up as scheduled downtime rather than a full stop, and it is usually announced with little notice. Orders placed for July and August delivery should carry a buffer of two to three weeks.
Shantou sits on the South China coast. Typhoon season runs roughly July to September. Ports in the region — Shantou, Shenzhen, Xiamen — close for one to three days during a direct hit, and vessel schedules take about a week to recover.
Direct production risk is modest: we batten down and lose a day or two. The risk that matters is at the port, and it is entirely outside anyone's control. Build a week of slack into any shipment booked between July and September.
The weeks immediately after Chinese New Year are the least intuitive bottleneck of the year. Plants are open, workers are back, and it still takes longer than you expect — because every order that was deferred in the previous six weeks now arrives at once. February and March are often the hardest months to get a new mould started.
If your project involves a new tool, start it before the holiday, not after.
| If you need delivery | Place the order | Reason |
|---|---|---|
| Before Chinese New Year (Jan–Feb) | 8–10 weeks ahead | Pre-holiday shipping crunch |
| March–April | Before the holiday, if possible | Post-holiday order pile-up |
| May–June | Normal lead time | The easiest window of the year |
| July–September | Add 2–3 weeks buffer | Power curbs and typhoon season |
| October–December | Add 1–2 weeks buffer | Pre-holiday congestion building |
Being honest about the boundaries is more useful than promising the impossible.
Most of our long-standing customers settle into an annual pattern without ever writing it down:
It is not glamorous, and it is the difference between a supply chain that runs and one that surprises you twice a year.
We will recommend resin, gram weight and neck finish, and quote unit price + mold cost within 24 hours.